| Pentagon
Renovation Project |
|
| Project Name: |
Pentagon Renovation Project Wedges 2-5,
Arlington, VA |
| Owner: |
US Department of Defense |
| Description: |
The Pentagon Renovation Wedges 2-5 is a
phased design/build renovation of 4 million square feet
of space in the Pentagon. Scope includes removal of all
hazardous materials, replacement of all building
systems, addition of new elevators and escalators and
installation of new security and telecommunications
systems. Project completion is scheduled for 2010. |
| Role on Project: |
Commissioning Consultant |
| Services Provided: |
Implemented the QuiCx Project Delivery
System for the Pentagon Renovation Liaison Branch of
Washington Headquarters Services to manage and track the
design, construction and closeout deliverables to the
Government.
Developed and implemented the Commissioning,
Decommissioning, Quality Control and Record Document
Management programs for the Design-Build Contractor. |


|
|
|
Smithsonian Institution |
| Project Name: |
Old Patent Office Building, Washington,
D.C. |
| Owner: |
Smithsonian Institution |
| Description: |
The Old Patent Office Building project was
a historic preservation of the third oldest building in
Washington D.C. It included new mechanical, electrical,
telecommunications, plumbing, security, fire alarm, and
fire protection systems, reconditioning. The interior
was modified to include galleries, office, retail, and
support spaces for the museum. |
| Role on Project: |
Commissioning Agent |
| Services Provided: |
Develop and execute the Commissioning Plan;
develop the master equipment list; review equipment submittals,
develop pre-functional checklist and functional performance
tests, direct onsite commissioning activities, and conduct
on-site functional performance testing.
Develop and facilitate the systems and equipment operator
training programs including video production of training
sessions.
Develop and implement construction document control
processes and protocol. Manage and administer the delivery
of the project record documentation including production
of CAD as-built documents, Operations and Maintenance
Manuals, and Systems Manuals.
Implement the QuiCx Project Delivery System for the
management of the project record documents. Provide
live streaming web cameras including production of time
lapse movies of construction progress. System is accessible
to 150 project users.
|


|
|
|
National Oceanic & Atmospheric
Administration |
| Project Name: |
NOAA Satellite Operations Facility,
Suitland, MD |
| Owner: |
National Oceanic & Atmospheric
Administration |
| Project Description: |
The facility houses the National
Environmental Satellite, Data and Information Services (NESDIS)
Satellite Operations and Data Processing Centers. The
design consists of a three-story tower with an
antenna to house the satellite operations and computer
center, and a high-tech office. NOAA is pursuing a
Silver Rating under the LEED certification system. |
| Role on Project: |
Commissioning Consultant |
| Services Provided: |
Providing commissioning consulting
services to the General Contractor, P.J. Dick
Incorporated in management, coordination and
implementation of the project commissioning
requirements.
|
 
|
|
|
Potomac Yards North and South Buildings |
| Project Name: |
Potomac Yard North and South Buildings,
Arlington, VA |
| Owner: |
Crescent Resources |
| Project Description: |
A 650,000+ square foot LEED office building consisting of a north and south tower. The U.S. Environmental Protection Agency has leased more than 400,000 square feet in two office buildings |
| Role on Project: |
Commissioning Support |
| Services Provided: |
Providing electrical commissioning
services in support of the project commissioning agent
Advanced Building Performance, Inc.
Implemented the QuiCx Project Delivery System to manage
the commissioning process including production of the
master equipment list, and pre-functional checklists.
|


|
|
|
Department of Environmental Protection |
| Project Name: |
Department of Environmental Protection -
Administrative Facilities, New York |
| Owner: |
NY Dept of Environmental Protection |
| Project Description: |
New construction of six (6) administrative
and policing facilities at various locations in New York. |
| Role on Project: |
DesignBuild Commissioning Agent |
| Services Provided: |
Developed and executed the Commissioning
Plan; developed the master equipment list; reviewed equipment
submittals, developed pre-functional checklist and functional
performance tests, directed onsite commissioning activities
and conducted on-site functional performance testing
Implemented the QuiCx Project Delivery System to manage
the commissioning process including production of the
master equipment list, and pre-functional checklists.
|


|
|
|
Asbury Park High School |
| Project Name: |
Asbury Park High School and Middle School
Additions and Alterations, New Jersey |
| Owner: |
NJ Schools Construction Corporation |
| Project Description: |
Asbury Park Middle School Project consists
of a 87,480 sq. ft. renovation & 50,825 sq. ft. expansion
to be completed in 2005. Asbury Park High School Project
consist of a 127,430 sq. ft. renovation & 57,305 sq.
ft. expansion to be completed in 2006. |
| Role on Project: |
Commissioning Consultant |
| Services Provided: |
Design phase services include development
of project flow charts, review of Design Intent and Design
Development documents and development of Commissioning
specifications for integration into the master specifications,
and development of the Commissioning Plan in accordance
with ASHRAE Guidelines
|


|
|
|
Baltimore/Washington International Airport |
| Project Name: |
Terminal A/B Expansion - BWI Airport, Maryland |
| Owner: |
Maryland Aviation Authority |
| Project Description: |
The Terminal A/B Expansion Project involves
the demolition of the existing Pier B connector, construction
of a two story Concourse B Connector, a two story Terminal
addition with a mezzanine and concessions area, a two
story Concourse A connector, and a two story Concourse
A. A total of 26 new gates will be established. The work
includes civil, structural, architectural, mechanical,
electrical, and baggage handling systems. |
| Role on Project: |
Quality Assurance/Commissioning Consultant |
| Services Provided: |
Implementation of QuiCx Project Delivery
System for the management of the contractors Quality Control
and Commissioning programs. |


|
|
|
Dulles Pedestrian Walkback Tunnel |
| Project Name: |
Dulles Pedestrian Walkback Tunnel - Dulles
International Airport, Virginia |
| Owner: |
Washington Metropolitan Airports Authority |
| Project Description: |
This project located at the Dulles International
Airport, consisted of a new passenger walkway equipped
with moving sidewalks that connects the Terminal to Concourse
B. The grand opening of the walkway was in November 2004. |
| Role on Project: |
Quality Assurance Consultant |
| Services Provided: |
Implementation of QuiCx Project Delivery
System for the management of the contractors Quality Control
program. |


|
|
|
Evolved Expendable Launch Vehicle Project (EELV) |
| Project Name: |
Evolved Expendable Launch Vehicle Project
(EELV) - Launch Complex 41, Cape Canaveral, Florida |
| Owner: |
Lockheed Martin Astronautics |
| Project Description: |
Design-Build construction project
consisting of multiple industrial and commercial
facilities, including the vehicle integration facility,
launch complex, mobile launch platform and space flight
operations center. The inaugural launch of the ATLAS V
rocket was in August of 2002. |
| Role on Project: |
Startup, Commissioning and Closeout
Consultant |
| Services Provided: |
Scheduled and directed mechanical equipment and
systems startup and commissioning. Developed and managed
the systems and equipment training programs. Managed the
development of the Systems Manuals in accordance to
ASHRAE Guidelines.
Developed and implemented construction document
control processes and protocols for both the Owner and
the Design Build Contractor. Managed and administered
the delivery of the project closeout documentation
including the master equipment list, spare parts list,
operations and maintenance manuals, and record drawings
and specifications.
|


|
|
|
|